Demolition work at pier landing stage completed
Ports of JerseyWork to demolish a pier's landing stage has been completed and the pierhead has reopened to the public, Jersey Ports has said.
Originally it had been hoped the work to remove Gorey Pier's deteriorating structure would be completed before the summer.
Ports of Jersey said it also resurfaced the pedestrian walkway and the newly installed railings would be painted to enhance both the area's appearance and overall safety.
Captain William Sadler, Jersey harbour master, said it was "an important milestone in our ongoing commitment to protecting and preserving Gorey Pier, it was essential for safety but also safeguards the historic granite pier for the community to enjoy for years to come".
Ports of Jersey said it hoped people would enjoy the "enhanced and safer" pierhead environment as it moved forward with future improvement plans.
Phase one of the demolition project involved the removal of the upper deck and supporting pillars of the aging concrete landing stage.
A temporary support bracing between the lower deck and the original pier structure was also installed.
Ports of Jersey said people may have noticed that the external staircase on the terminal building, which provided access for authorised personnel, had been removed after ground investigations found it was no longer structurally sound.
It added it wanted to thank harbour users, local businesses, residents and visitors for their patience during the works.
Follow BBC Jersey on X,Facebook and Instagram. Send your story ideas to channel.islands@bbc.co.uk.