Crane set to lift collapsed bridge out of harbour
Work to repair a bridge which collapsed into a city's harbour is set to begin.
Pero's Bridge in Bristol, which could lift to allow boats under it, was left partially hanging due to a mechanical failure in the summer. It then toppled again, collapsing into the water on 31 October.
Earlier this month, a Bristol City Council report found the bridge was unable to be properly tested for almost a decade before its collapse due to the weight of padlocks attached to it.
Over the next few days, a crane on a barge will "carefully lift the three spans of Pero's Bridge and transport them to dry dock for a detailed inspection", a council spokesperson said.
The pedestrian bridge connecting Narrow Quay and Canon's Road was known to be in need of structural repairs.
Footage showed it closing slowly before suddenly falling during a routine test lift in August.

The council said an engineering assessment indicated external vibration was the most likely contributory factor to the collapse.
A specialist recovery operation, estimated to cost about £280,000, will remove the bridge spans and transport them to Albion Dry Dock.
The local authority hopes the repair work and reinstatement will be finished before summer 2027.
The cost of the recovery operation was already included in the approved £1.51m budget for a planned £1.51m refurbishment of the bridge, it said.
Follow BBC Bristol on Facebook, X and Instagram. Send your story ideas to us on email or via WhatsApp on 0800 313 4630.