Major railway line to close for a month as work is carried out
Network RailA major stretch of railway line will close for a month with passengers warned to expect disruption.
Engineers will work between Chester and Holyhead, on Anglesey, renewing track and other infrastructure.
To allow the work to be completed, the North Wales Coast line will close for four weeks from Saturday 9 January until Saturday 6 February 2027.
Network Rail's Emma Osborn called the £25m being spent a "once-in-a-generation investment", but admitted it would cause "temporary disruption" to passengers.
Osborn said "years' worth of complex work" would be brought together into one intensive programme.
This would mean it could be delivered more efficiently without a prolonged series of disruptive weekend closures.
"The long-term benefits for passengers and freight customers will far outweigh this temporary disruption, with a safer, more reliable railway that is better equipped to support the increased number of services now running across North Wales," she added.

From Saturday 9 January, the line will be closed for three weeks, between Chester and Holyhead, including the Conwy Valley line and Llandudno Junction to Llandudno.
During the fourth week of the improvement works, it will just be the stretch between Llandudno Junction and Holyhead that will be closed.
Rail replacement services will operate during the closure, with details expected to be confirmed in autumn 2026.
What will the £25m investment include?
- Renewing track through the Grade I-listed Conwy Tubular Railway Bridge, where the existing track dates back to 1978
- Major track and drainage improvements in Bodorgan Tunnel, replacing infrastructure dating back to 1972 and helping reduce the risk of flooding
- Track renewal and ground improvements at Penmaenbach, where sections of track were last renewed in 1986
- Track and points improvements at Holyhead and Llandudno
- Platform improvements at Llandudno Junction
- Work at four level crossings, east of Bangor
- Around £1.4m of vegetation management across nine locations, alongside extensive maintenance throughout the route
- Two new fully accessible footbridges at Prestatyn and Abergele, supporting the closure of four high-risk level crossings
Network RailTransport for Wales' planning and performance director Colin Lea said "essential track maintenance", alongside tunnel drainage, and new accessible footbridges will "help deliver a more reliable service and better stations" for passengers.
Passengers planning to travel over the period of works in early 2027 are advised to check the Avanti West Coast and National Rail Enquiries websites for the latest travel information.