Landowners decide not to continue legal bid to stop A5
BBCA group of landowners have said they will not take another legal challenge over a decision to build one of Northern Ireland's largest ever road projects.
Proposals to build a new dual A5 dual carriageway between Londonderry and Aughnacloy in County Tyrone go back almost 20 years but have been beset by funding and legal issues.
On Tuesday, a group against the A5 scheme said they had "reluctantly" decided not to appeal that decision to the Supreme Court.
In a statement the group said they did not have the "financial resources to pursue the litigation any further", but "remain firmly of the view that it was right to challenge the decision taken by the Department for Infrastructure to proceed with the A5 scheme".

The 58-mile stretch of road that traverses the west of Northern Ireland known as the A5, has made many headlines in recent years.
More than 50 people have died on the road since 2006.
Campaigners who want a new dual carriageway say the current road is not safe and claim its out-dated design increases risk of mistakes and accidents.
But others have raised opposition to the amount of land and farms that will be impacted by a new road as well as environment concerns around the construction of a carriageway.
Last year a group of residents, landowners and farmers known as The Alternative A5 Alliance took a legal challenge to stop work on the roads.
A judge found the project should not go ahead, saying the Department for Infrastructure's plans did not comply with climate change targets.
The department then took the case to the court of appeal.
In October, Lady Chief Justice Dame Siobhan Keegan said that while the scheme would increase emissions it was a priority investment and should be go ahead.
The total cost of the cross-border project is estimated to be in the region of £1.7bn.
The Northern Ireland Executive committed about £1.2bn when the final plan was announced by ministers in late 2024.
Irish government funding of €600m (£509m) for an upgrade of the road was announced in February 2024.
Almost £200m has now been spent on the project, despite work having yet to start on the road.