Rock barrier plans progress for landmark beach
Peter SPlans to build a rock barrier on a Dorset beach that is part of a Unesco World Heritage Site have moved forward.
Councillors have approved an £11m business case for the work at Chesil Cove, Portland.
The southern end of the existing sea wall could fail during the next significant storm, a council cabinet meeting was told.
The existing sea barrier, built in 1965, has a promenade, with steps leading down a sloping rock wall to the shingle beach.
It offers vital protection to an area prone to landslips, as well as 51 homes and a cafe, a council report said.
The report said the rock barrier would be "constructed on the beach fronting the seawall".
It added: "The rock revetment would extend approximately 26m (85ft) from the base of the seawall encroaching into the Dorset & East Devon World Heritage Site."
Dorset CouncilGovernment advisory body Natural England has raised no objection, it said.
The current wall would be reinforced by a new sheet steel wall with a capping beam along part of it.
In October, the council carried out short-term repairs to part of the wall, which it said was badly eroded.
Construction for the main project would begin in March 2028 and end in June 2029, cabinet members were told.
They approved the outline business case and a council contribution of up to £3.1m towards the £11m total cost.