Closed 'unsafe' road given possible opening date

News imageBBC An aerial shot of the unfinished and deserted road near Wanborough. There are fields either side of the Tarmac single-lane carriageway and walking paths immediately next to the road.BBC
The road was built to service 8,000 new homes on the edge of Swindon

Work to make an unused £40m road safe could begin as soon as January.

The Southern Connector Road was designed to connect the New Eastern Villages development of 8,000 homes near South Marston in Swindon with the M4.

The road was meant to have been finished in 2023 but was delayed after it was deemed unsafe when cracks appeared in the carriageway and movement was felt in the road's bridge.

Swindon borough councillor Nick Gardiner said a contractor for the immediate bridge repairs was expected to be appointed in December, with work planned for January.

According to the Local Democracy Reporting Service (LDRS), if deadlines are met and the correct technology is in place, the road could be open to construction traffic from February.

Gardiner, the council's cabinet member for highways and transport, said: "We will then be determining what is needed to be able to get it to the point where it is then deemed safe, so that we can open it as a normal public road."

How did we get here?

The unfinished road was handed over to Swindon Borough Council after constructors Buckingham Group went into administration in September 2023.

Vistry, the property developer of the Lotmead section of the New Eastern Villages development, is part funding some of the repair work, but Swindon Borough Council is paying for the repairs to the bridge to get the road open for construction traffic.

It is not yet clear when the road will be fully open to traffic.

News imageLocal Democracy Reporting Service A large group of people are pictured sitting around a long table. There are others standing around the table. Most of them are looking at a man who is standing at the head of the table. The room they are in is long with white walls and beams up to the apex ceiling.Local Democracy Reporting Service
Those who attended a public meeting heard that the situation was "very difficult"

Those who attended a public meeting on Thursday said they had been "suffering like hell for the last four to five years" and construction traffic from the housing development had been making houses shake.

A few residents questioned how the council and Vistry would make sure construction traffic was travelling down the correct route once the road was opened.

Gardiner said that new number plate recognition technology would be used to identify lorries entering and leaving the site.

Council leader Gary Sumner, who also attended the meeting, said it was a "very difficult situation" but that progress was being made.

Sarah Rolls, a resident of Merlin Way, said she left the meeting "slightly more confident" that the road would open.

News imageJason Spickett An aerial image of a road surrounded by fields and running through a building siteJason Spickett
The Southern Connector road as pictured in 2025

Photographer and Swindon resident Jason Spickett took drone pictures of the Southern Connector Road in 2025.

He previously worked from an office in Wanborough and said: "I had hoped I'd be able to drive back on that road but it unfortunately never got to that stage.

"It [the road] has just never happened."

Additional reporting by Kirsten Robertson