Vauxhall Bridge 'could have to shut to buses'
Bloomberg via Getty ImagesVauxhall Bridge will have to shut to buses and fire engines within two to four years unless about £60m is invested in repairs, Transport for London (TfL) has warned.
The crossing, which is the busiest bridge in central London, could even have to close fully to vehicles in four to 10 years without the necessary work, it said.
TfL has applied to the government's £1bn structures fund for the money, with the successful bids due to be announced soon.
David Rowe, TfL's director of investment planning, told BBC London that the bridge's waterproofing had "failed" and "we will see progressive deterioration unless action is taken, which is why these bids are so important for us".
Some 44,000 vehicles use Vauxhall Bridge every day, including about 2,450 buses and 1,850 heavy goods vehicles.
TfL's application to the Department for Transport (DfT) scheme reveals how much trouble the crossing is in.
It notes that while the bridge's waterproofing was renewed in 2020, there has been "significant deterioration of the underside steelwork" and "key structural elements [are] now in very poor condition".
Fascia panels on the 120-year-old Grade II*-listed bridge are also "at risk of detaching and falling on to the river below, posing a safety hazard to passing vessels".
Bloomberg via Getty ImagesAn 18-tonne weight limit was introduced to the bridge in July to slow its deterioration, but the letter says without investment, a 7.5-tonne limit would have to be introduced by 2030, meaning the bridge would be shut to buses, coaches and many emergency service vehicles.
Even with such a measure, the bridge would need to shut to all vehicles by 2036 if significant work is not carried out.
The letter states the cost of the entire programme of work is the "equivalent to approximately two years of TfL's entire planned structures renewals budget".
Rowe would not give an exact figure but agreed it was about £60m, with the transport authority currently spending £30m a year on renewing its structures.
He told BBC London if the bid was unsuccessful, TfL would have to "look very, very carefully about where we prioritise our renewals".
"We have a certain amount that we can invest every year but with projects as big as Vauxhall Bridge... we really, really do need support alongside what we can bring".

TfL currently spends £860m a year on maintaining its entire network, which includes roads, bridges and the Tube.
Nevertheless, it says it should be spending £1.2bn a year, with the backlog in the overall work required estimated to have grown to £6.5bn.
Rowe explained the body's finances had been hit by the loss of an operating grant it received from the government until 2018 and "the impact that we've seen from Covid in terms of reduced people on our networks and therefore reduced income".
Data released in a Freedom of Information request reveals that of the seven road bridges that cross the Thames that TfL manages, three - Vauxhall, Lambeth and Westminster - are rated as being in a "very poor" state, with the other four - Twickenham, Kew, Chiswick and Battersea - marked as "poor".
Asked whether the authority should be criticised for the state of the structures it manages, Rowe said that this would be "not fair" and it was investing "very significant amounts… to keep them operable but we have a backlog due to that reduced income".

The structures fund was launched by the DfT in April with authorities across the country bidding for part of a £1bn pot.
In addition to Vauxhall Bridge, TfL has appealed for financial help for the Croydon Flyover in south London, which has some 40,000 vehicles using the road daily and 30,000 travelling underneath it.
It is noted as being in "a critical state of deterioration" due to water damage to the steelwork, with "several essential components... already assessed as life-expired".
TfL also set out in another letter to the DfT a total of 13 schemes across London, including applications made by some boroughs, which are "network priorities" because any further closures or restrictions on them "would have significant adverse effects on the immediate wider community and economy".
Six of those, which all already have restrictions for safety concerns, are marked as "the highest priority":
- Albert Bridge, Kensington and Chelsea (closed to vehicles since February)
- Broadmead Bridge, Redbridge (closed to vehicles since July 2023)
- Croydon Flyover (designed to have a 40mph speed limit but limited to 30mph)
- Hubert Grove Footbridge, Lambeth (closed since November 2023)
- Richmond Bridge, Richmond upon Thames (18-tonne weight restriction)
- Vauxhall Bridge (18-tonne weight restriction)
In total, the cost of such works for the 13 projects would exceed £400m.
"We need very significant levels of capital right across the capital to address the problem," Rowe said.
London's Mayor Lord Khan told BBC London the city had struggled with its bridges because "we had anti-London governments in eight of my last 10 years".
"The good news is this government has notably increased massively the capital funding that TfL gets but also that we can bid now for infrastructure projects."
When approached, the DfT would not give a date about when the successful bids will be announced, only that this would happen "in the autumn".
Listen to the best of BBC Radio London on Sounds and follow BBC London on Facebook, X and Instagram. Send your story ideas to hello.bbclondon@bbc.co.uk
